School construction progress at Milford

The new school construction project is moving right along at Milford. The MAPS #124 district reports work, so far, is ahead of schedule.  Weather permitting, completion is looking like August of 2017.

The storm sewer has been installed. Floorin g pads for the acedemis and extra-curricular wings have been leveled and compacted.  Masons are at work this week setting up silos for mortar production and to begin the process of receiving brick and block in preparation for installation. 

The district also report waterproofing has been completed around the foundation on the north and east side of the project.  Parking lot curbs and sidewalks have been roughed-in.  Concete pouring is expected later this month.  Ameren has also relocated and replaced power poles for the new building.  

94.1 WGFA